Bringing Students & Staff Together in One Facility

Oak Grove School District #68

$3 million

budget

17,500

sq. ft

Gallery

The Challenge


Following years of master planning and cost analysis, the board of education decided to consolidate all K-8 students and staff into one facility—adding 12 air-conditioned classrooms, a multipurpose gym, a science lab, restrooms and expanded administrative offices. These renovations were the building’s first major upgrades since the 1970s.

 

KEDbluestone Solution


In addition to providing all new electrical, HVAC and plumbing to support the additions and renovations, we installed special data, telecommunications and fire alarm systems as well as a new secure entry with card access. Working over an 18-month construction period, we took a phased approach—carefully planning all utility work to ensure the school remained operational with minimal disruption to staff and students.