Designing a New Dialysis Treatment Center
THE CHALLENGE The Proctor Professional Building needed to renovate its existing basement space into a new dialysis treatment center. The ceiling height brought challenges, as
What began as a normal HVAC upgrade for this 1940s-era school turned into a more comprehensive solution when asbestos was discovered in the piping routed through the building’s tunnels. Even with the addition of abatement work, the project still needed to be completed during the eight-week summer break.
We brought in an abatement contractor to address the asbestos issue, a process that took about three weeks before any additional work could begin. Once abatement was complete, we installed all new heating and cooling equipment, including boilers, pumps and piping. We also made significant upgrades to the school’s electrical infrastructure to accommodate the new system’s added load. All work was done during a shortened five-week timetable.
THE CHALLENGE The Proctor Professional Building needed to renovate its existing basement space into a new dialysis treatment center. The ceiling height brought challenges, as
THE CHALLENGE OSF HealthCare Jump Trading Simulation & Education Center needed to transform their empty, existing shell space into a new on-site nursing student training
THE CHALLENGE El Paso Park District needed to build a new recreation center. The park district requested that the new facility include four multi-purpose gymnasium
THE CHALLENGE OSF needed to expand their parking deck to accommodate the new Cancer Institute. The parking deck needed a walkway connection to the hospital’s
We will be glad to answer your questions.
We look forward to working with you.
© 2024. Copyright. KEDbluestone. All Rights Reserved