Project

Modifying Solutions in the Field to Fit Budget & Schedule

East Peoria Community High School

$5 million

budget

80,000

sq. ft

Gallery

The Challenge

Air conditioning the remaining 40% of this high school proved the roof wasn’t strong enough to house an air-handling unit. A tight budget for both HVAC and lighting upgrades, along with a summer-only work schedule, added to the challenge.

 

KEDbluestone Solution

We installed a 300-ton chiller as part of a new zoned HVAC system that allows for greater energy efficiency. To accommodate the existing structure, we modified ductwork in the field and placed the air handling unit on platforms set atop welded steel beams cut through the roof. We also worked with the local utility company to acquire $40,000 in incentives for new LED lighting, which helped keep the project within budget. The entire job, including asbestos abatement, was completed during the summer break as scheduled.

Location/Map

View our Other Projects