The Challenge

The multi-specialty clinic had outgrown the space and needed an expansion and renovation. OSF was looking to add 40 additional exam/procedure rooms to accommodate their growing patient needs. The building lacked humidity control and the HVAC system was ineffective. We were asked to address these problems in a cost-conscious fashion, while keeping the clinic open.

 

KEDbluestone Solution

In order to keep the clinic operational, we carefully phased in our renovations. New boilers, chillers, and humidifiers were replaced for patient and staff comfort. We added full building automation, which allowed the HVAC to be controlled remotely. A new emergency generator and power system was installed to ensure continuity in services. The building fire protection and plumbing systems were upgraded. The result was a much more comfortable space for the clinic.